Blog

How a BMS Guards Your Electricity Bill: Load Shedding and Demand Limiting

How a BMS caps peak demand with load shedding, demand limiting, duty cycling and staggered starts — and why shaving peak kW saves real money under TNB RP4.

Tan Kok XinTan Kok XinBuilding Automation & BMS Fundamentals
Illustration of an operator watching a demand graph approach its limit, with three loads marked to shed

Part 14 of 16 in Cobler's Building Automation and BMS Fundamentals course. New here? See the course page.

On a hot weekday in the office tower, the chillers, pumps, air handling units, lifts and lights are all busy at once. The busiest half hour is usually 2:30pm to 3:00pm.

On Thursday 17 September 2026, that half hour reached 1,600 kW, and it set the month's maximum demand. That one half hour can decide a large part of the month's electricity bill.

In Part 12 and Part 13 we saw how the building management system (BMS) runs the chiller plant and the air side. Together they take the largest share of the tower's electricity on a hot afternoon. So can the BMS trim that demand for a few minutes at a time, to lower the monthly demand charge?

It can, by watching the building's power during each 30-minute period. When needed, it briefly eases or delays loads that can wait, so the half-hour average stays below a limit we choose.

But that only saves money on a tariff that charges for maximum demand in kW. Which half hours count depends on the tariff too. All of the course's TNB (Tenaga Nasional Berhad) tariff detail for BMS control is here, in one place.

Energy and demand

Picture two cars that each travel 100 kilometres in a day. One drives at a steady pace, and the other crawls, accelerates hard, then crawls again. They cover the same distance, but the second car needs a bigger engine to cope with its bursts.

An electricity bill can charge for both things:

  • Energy, in kilowatt-hours (kWh), is how much electricity the building used over the month. That's the distance travelled.
  • Demand, in kilowatts (kW), is how fast the building was drawing power at its busiest time. That's how hard the driver accelerated.

Two buildings can use the same kWh in a month and pay very different demand charges, because one of them had a much higher peak.

Worth knowing: the Electricity course explains the difference in Power vs Energy: kW and kWh. It goes through each line of a bill in Your TNB Bill, Line by Line.

Why charge for demand at all? Because every cable, transformer and power station upstream must be sized for your busiest moment, not your average one. That capacity is reserved for you, whether you use it for half an hour or all day.

Which tariffs charge for demand

So does every building pay for demand? No. RP4 is the TNB tariff structure in force since 1 July 2025. Under RP4, the demand charge has two parts, Capacity and Network, both charged per kW, and it applies only to some tariff categories:

Tariff (Peninsular Malaysia, RP4)

Demand charge per kW each month

Which half hours count

LV non-domestic General or ToU

None (Capacity and Network are charged per kWh)

Not applicable

MV non-domestic General

RM29.43 + RM59.84 = RM89.27/kW

Any half hour, any day

MV non-domestic ToU

RM30.19 + RM66.87 = RM97.06/kW

Only 2pm to 10pm, Monday to Friday

LV means low voltage, the 400/230 V supply small buildings take from the street. MV means medium voltage, where a larger building takes an 11 kV supply into its own substation. These totals don't apply to high voltage (HV) or special tariff categories.

Time of use (ToU) tariffs charge different energy rates at different times of day. On MV ToU, only the weekday peak window counts for demand, and weekends are off-peak throughout.

The office tower is on MV non-domestic General. So every half hour of the month can set its maximum demand, including early mornings and Saturdays.

For contrast, take our example shoplot, a made-up three-storey shoplot in Petaling Jaya with a café and a small office. It's on LV General, so it has no per-kW charge at all. For the shoplot, the useful saving is total kWh, and demand limiting wouldn't lower its bill.

So before setting up any demand logic, check which tariff the building is on. You can try your own numbers with our maximum-demand calculator. Part 4 of our Understanding Your Electricity Bill course, Maximum Demand: Why One Bad Half-Hour Costs So Much, covers the demand charge in full.

The 30-minute average

Now, what exactly does the meter count? TNB measures maximum demand (MD) as the highest metered 30-minute average kW in the month.

The meter works out how much energy the building used in a half hour, and turns that into an average power. Two times the kWh in a half hour gives the average kW, because a half hour is half of an hour.

Because it's an average, a short burst counts for little. Say the building draws an extra 300 kW for 2 minutes. Averaged over 30 minutes, that adds only 300 × 2 ÷ 30 = 20 kW to the half-hour average.

But a burst that lasts most of the half hour counts almost in full. That tells the BMS what to aim for. It can let a brief surge go, as long as each half-hour average stays below the limit.

So let's go back to that Thursday. Its highest half hour, 2:30pm to 3:00pm, reached 1,600 kW.

Bar chart of the office tower's average demand in each half hour from 12:00 to 17:00 on 17 September 2026. Three half hours from 2pm to 3:30pm are above a dashed 1,550 kW limit line, with the highest at 1,600 kW

To hold 1,550 kW that day, the BMS would have needed to trim three half hours: by 20, 50 and 30 kW.

The demand charge on this bill was 1,600 kW × RM89.27 = RM142,832. Now say the BMS had held every half hour of the month at or below 1,550 kW. Then the charge would have been 1,550 × RM89.27 = RM138,368.50, a saving of RM4,463.50 for that month.

Forecasting the half hour

So how does the BMS keep each half hour under 1,550 kW? First it needs a power meter it can read on the building's incoming supply. Then it does simple arithmetic all through each half hour:

  1. It adds up the kWh used so far in this half hour.
  2. It estimates the kWh for the minutes left, assuming the present power continues.
  3. It adds the two and turns the total into a half-hour average.
  4. If that forecast is heading above the limit, it acts now, while there's still time to pull the average down.

Let's work one through with the 1,550 kW limit. A 1,550 kW average over half an hour is 775 kWh. Twenty minutes in, the meter shows 520 kWh used, and the building is drawing 1,650 kW.

If that continues for the last 10 minutes, it adds 1,650 × 10 ÷ 60 = 275 kWh. That's a total of 795 kWh, which is an average of 1,590 kW, so it's over the limit.

To stay at 775 kWh, the last 10 minutes can use only 255 kWh, which is an average of 1,530 kW. So the BMS must shed about 120 kW for the rest of the half hour.

Wait five minutes, and the same overshoot must come out of 5 minutes instead of 10. So the BMS must shed about 240 kW, twice as much. And acting after the half hour has ended is too late. Once a half hour closes above the limit, that's the new maximum for the month.

Try it

Loading the interactive

There are two practical points. First, the building's own meter and TNB's meter may not start their half hours at exactly the same moment. So set the BMS limit with a margin below the level you want to avoid.

Second, check that the meter reading reaches the BMS reliably. Part 10 covered scaling, timestamps and stale data, and a limit built on a frozen reading does nothing.

The priority list

So the BMS knows it must shed 120 kW. But shed what? Let's name the two ideas first.

Demand limiting is the strategy, keeping each half-hour average under the limit. Load shedding is the main tool. When the forecast is too high, the BMS temporarily switches off or eases loads that can wait.

The BMS decides what to shed from a priority list, which the facility team writes and the BMS follows:

  • Shed first: loads nobody will notice for a few minutes. Examples are a decorative fountain pump, a bank of water heaters, and a small nudge to zone cooling setpoints. Car park ventilation fans can go too, but only while the car park's air quality allows it.
  • Shed later, if needed: larger cooling loads, where most of the sheddable kW sits. In the office tower, the chiller plant runs near full power only on hot afternoons, so it uses about 35% of the month's electricity. But on those afternoons its 855 kW (Part 12) is more than half of the 1,600 kW peak. Many chillers accept a signal that limits how much power they may draw.
  • Never shed: life-safety systems, lifts, the server room and any critical process equipment.

As the forecast rises towards the limit, the BMS works down the list. It starts with the least important loads and moves on only if the forecast is still too high.

When the next half hour starts and there's room again, it restores the loads in reverse order, in stages. Restoring everything at once can cause a new peak, because each load comes back hungry.

In a tropical building, a small setpoint relaxation is often the most useful shed. Say the BMS lets the zones served by AHU-12A drift up by half a degree for a few minutes.

Each VAV box closes a little, and the static pressure reset from Part 13 lets the fan slow down. So the chilled water load falls.

A large air-conditioned floor holds its temperature for a while, so a short trim like this usually goes unnoticed. It's a much smaller change than the unoccupied setback in Part 7, which lets an empty building warm up overnight.

Duty cycling and staggered starts

There are two more tools, and both lower the peak by changing when equipment draws power, instead of switching it off for long.

Duty cycling takes turns. Say the building has several similar units, such as four cooling tower fans or a bank of small units. The BMS runs them in a rotating pattern of a few minutes on and a few minutes off.

The total work stays about the same, but less of it happens at the same moment. And rotating which unit rests spreads out the wear.

Staggered start-up brings large equipment on one item at a time, instead of all together. The reason is easy to get wrong.

You'd think the problem is the high current a big motor draws in its first seconds. But that lasts only seconds, so it adds very little to a 30-minute average. The bigger problem is what happens next.

Say a building has warmed up overnight. Every chiller, pump and AHU that starts together then runs at full output for a long time to cool it down. That pull-down period can last well over half an hour.

So starting them in steps, with a pause between each, spreads the pull-down load and lowers the half-hour average.

Worth knowing: large centrifugal chillers are often started through a drive or soft starter, instead of being thrown straight onto the supply.

Whether a start-up peak costs money depends on the tariff:

  • MV General (the office tower): a morning start-up at 7:30am counts like any other half hour. If the pull-down is the highest half hour of the month, it sets the MD.
  • MV ToU: a morning start-up before 2pm is off-peak and doesn't set the billed MD. The risk moves into the peak window. Examples are a second chiller staging on at 2pm, or the whole plant restarting after a power dip at 3pm. Those are the moments to stagger.

What it's worth

So what's all this worth? On the office tower's MV General tariff, each kW of maximum demand costs RM89.27 a month. Trimming the 50 kW from the earlier example is worth RM4,463.50 in a month. That's RM53,562 over a year, if the building holds the lower limit every month.

On an MV ToU tariff, the same 50 kW would be worth 50 × RM97.06 = RM4,853 a month. But that's only if the trim happens inside the 2pm to 10pm weekday window.

Three limits keep these numbers honest:

  • Demand and energy are separate charges. Shedding a load for a few minutes saves little energy, and some of it comes back later as the load catches up. Trimming the peak and trimming total kWh are two different savings, on two different lines of the bill.
  • The strategy decides the saving. A BMS knows nothing about your tariff. It reports demand half hour by half hour, and it follows the strategy you set. The facility team decides which loads may be shed, where to put the limit and how far a setpoint may drift. Set the limit too low and the building runs short of cooling, and set it too high and nothing is saved.
  • Comfort comes first. A demand limit that leaves tenants warm every afternoon will get overridden, and an overridden limit saves nothing. Part 8 covered overrides.

And there's one more catch. Maximum demand is the single highest half hour of the month. So a limit that holds on 29 days and fails on one afternoon saves nothing. The BMS has to hold it every day, with a margin.

None of this needs new equipment in a building that already has a BMS and a power meter it can read. It needs a known peak, a sensible limit and a clear priority list.

Proving it

So now we've seen everything a well-set-up BMS should do. It runs the plant, runs the air side and holds down demand, on top of the loops, sequences and schedules from earlier parts. But so far we've only described it.

So how does anyone know the BMS actually does all this, before the owner accepts the building from the contractor? We have to test it, in Part 15: Proving the BMS Works.

Check your understanding

1. A building on MV ToU has its highest demand of the month at 8:00am to 8:30am on a Monday, when the plant starts. Does staggering that start-up lower its demand charge?

Show the answer

No. On MV ToU, only half hours from 2pm to 10pm on weekdays count for the demand charge. So an 8am peak isn't billed as MD, and the building should look instead at its highest half hour inside the peak window.

On MV General, like the office tower, the same 8am peak would count, and staggering would help.

2. Twenty minutes into a half hour, the forecast says the average will be 1,590 kW against a 1,550 kW limit. Why must the BMS shed more than 40 kW?

Show the answer

Only 10 minutes are left to pull down an average that covers the whole 30 minutes. The first 20 minutes can't be changed, so the last 10 minutes must cover all of the difference.

In the forecasting example, the building had to drop from 1,650 kW to about 1,530 kW. That's a shed of about 120 kW, to bring the half-hour average down to 1,550 kW.

Recap

  • A demand charge applies only on some tariffs. MV General counts any half hour at RM89.27/kW, MV ToU counts only 2pm to 10pm on weekdays at RM97.06/kW, and LV has no per-kW charge.
  • Maximum demand is the highest metered 30-minute average in the month.
  • So a BMS forecasts each half hour and sheds loads from a priority list before the half hour ends.
  • Setpoint relaxation, duty cycling and staggered starts lower the average without much loss of comfort.
  • The limit has to hold every day of the month, and the BMS only follows the strategy the facility team sets.

Go deeper on video (optional)

This video explains demand charges and ways to shave a peak. It comes from outside Malaysia, so its interval length and the hours when demand counts may differ from TNB's.

For Malaysian bills, use the tariff and maximum demand rules above. You don't need it for the next part.

This is Part 14 of 16 in Cobler's Building Automation and BMS Fundamentals course. Previous: How a BMS Runs the Air Side: VAV, Static Pressure Reset and Fresh Air. Next: Proving the BMS Works: Commissioning and Handover.

Cobler builds CobiNeural, a platform that shows a facility team its building's energy, water and indoor air data as live numbers across the whole site. To see how your building performs, talk to us.

FAQ

Frequently asked questions

Ask us about this topic

Something in this article you want to dig into — or a situation in your own building it doesn't quite cover? Send us your question. We don't run public comments; the team replies to you directly by email.

0/500

Keep reading