Blog

How a BMS Optimises the Chiller Plant: Staging and Temperature Reset

How a BMS sequences chillers and resets chilled-water and condenser-water temperatures to cut energy, so the same plant runs efficiently or wastefully.

Tan Kok XinTan Kok XinBuilding Automation & BMS Fundamentals
Illustration of a BMS controller linked to a cooling tower and four chillers, with one chiller running

Part 12 of 16 in Cobler's Building Automation and BMS Fundamentals course. New here? See the course page.

It's a hot weekday afternoon in the office tower, and every AHU (air handling unit) in the building is asking for cold water. Down in the basement, the chiller plant has to supply it.

The plant, which is the chillers, pumps and cooling towers together, is the building's largest single electricity user. It takes about 35% of the building's electricity.

So how does the BMS (building management system) decide how many chillers to run, and how cold to make the water? In Part 11 we finished connecting and looking after the BMS, and now we put it to work.

Chiller plant control comes down to three decisions the BMS makes again and again:

  • Staging decides how many chillers run.
  • Chilled water reset decides how cold the water leaving the chillers needs to be.
  • Condenser water reset decides how cold the cooling towers should make the water that carries heat away.

None of these needs new equipment, because they're all settings and sequences in the BMS. So two identical plant rooms, with the same chillers, pumps and towers, can have very different electricity bills. It all depends on how well those three are done.

The plant and kW/RT

Let's start with a quick refresher on the plant itself. If it's all new to you, the Cooling Fundamentals course explains it properly.

A water-cooled chiller plant moves heat from the building to the outdoor air, using two water loops with the chillers between them.

  • The chiller makes cold water. Inside it, a compressor drives a refrigerant around a loop. The refrigerant absorbs heat from the building's water and rejects it into a second water loop.
  • Chilled water pumps send the cold water out to the AHUs. In the office tower it leaves the chillers at 6 °C and comes back at 12 °C, having picked up heat from the air.
  • Condenser water pumps carry the heat the chiller rejects up to the cooling towers on the roof.
  • Cooling tower fans blow air through the falling condenser water. Some of the water evaporates, which cools the rest, and it flows back down to the chiller to collect more heat.

Two units describe how the plant performs. Cooling is measured in refrigeration tons (RT), where 1 RT = 3.517 kW of cooling. One RT is also 12,000 BTU/h, the unit many chiller catalogues use.

Efficiency is measured in kW/RT, the electrical kilowatts the plant draws for each ton of cooling it delivers, so lower is better.

An efficient plant runs at around 0.5 to 0.7 kW/RT, while a poorly run one can go above 1.0 kW/RT for the same cooling. The office tower's plant was designed for 0.85 kW/RT, and it measures 0.95 kW/RT.

Worth knowing: these figures depend on whether you measure the chillers alone or the whole plant with its pumps and towers. The office tower figures are for the whole plant, and the Cooling course's lesson on COP, EER and kW/RT explains the difference.

The office tower has three 500 RT centrifugal chillers, so 1,500 RT is installed in total. Two are "duty" chillers that share the load, and one is standby, so 1,000 RT is normally available. The peak cooling load is about 900 RT.

Worth knowing: everything the BMS commands here is driven by three-phase electric motors, often through a variable speed drive (Part 2). That covers the compressors, pumps and tower fans. For now, what matters is which machines run and at what temperatures.
Water-cooled chiller plant for the office tower showing the chilled water loop at 6 degrees C supply and 12 degrees C return to the AHUs the condenser water loop to the cooling towers and the three things the BMS controls: how many chillers run the chilled water setpoint and the condenser water setpoint which cannot go below the outdoor wet-bulb temperature

Three BMS decisions for the plant: how many chillers run, how cold the chilled water is, and how cold the towers make the condenser water.

Flow and delta-T

Before the BMS can decide how many chillers to run, it needs to know the cooling load. That's how much heat the building is sending back to the plant right now. So how does it measure that? Well, it works it out from the water.

The chilled water picks up heat in the AHU coils, so it comes back warmer than it left. We call that temperature rise the delta-T (ΔT, where "delta" means difference).

The cooling delivered depends on two things, how much water flows and how much it warms up. For water:

cooling (kW) = flow (litres per second) × 4.19 × ΔT (°C)

The 4.19 is the energy, in kilojoules, needed to warm one litre (about one kilogram) of water by 1 °C. The Cooling course's lesson on pumps, valves and flow explains this formula, the pumps and the valves in more detail.

The BMS measures the load with a flow meter on the chilled water pipe and temperature sensors on the supply and return.

Let's take the office tower at its peak of about 900 RT, which is about 3,165 kW of cooling. With the design ΔT of 6 °C (6 °C out, 12 °C back), the flow needed is:

3,165 ÷ (4.19 × 6) ≈ 126 litres per second.

Keep that 126 in mind, because we'll come back to it when the ΔT goes wrong.

Staging

So now the BMS knows the load. On most hours, the building needs much less than the installed capacity. So which chillers should run, and how many?

You might think it's best to spread the load and run both duty chillers all day, each carrying half. On a morning when the load is 350 RT, that means two 500 RT chillers, each running at 35% of capacity.

But one chiller could carry the same load at 70%, and the second chiller adds overheads for no extra cooling. Each running chiller brings its own condenser water pump and its share of tower fans, and every machine has some losses from running at all.

Staging, also called sequencing, is the part of the sequence that avoids this. The BMS runs the fewest chillers that can meet the load, each loaded in its efficient range. In the office tower on a typical weekday:

  1. Morning, load 350 RT. One chiller runs, at about 70% of its capacity.
  2. Afternoon, load rising towards 800 RT. Before the running chiller hits its limit, the BMS stages up.
  3. Evening, load falling. When one chiller could carry the load again, the BMS stages down and stops the second chiller.

When it stages up, the BMS starts the pumps for the second chiller, proves flow, and then starts the chiller. That start-up order is the interlock sequence from Part 6.

The two chillers now share the load at about 80% each. And when it stages down, the remaining chiller stays well loaded.

Each stage-up and stage-down point has a deadband and a time delay. We met the deadband in Part 4, as a gap between the "start" and "stop" conditions. Together with a delay, it stops the plant switching a chiller on and off every few minutes as the load wobbles.

Which loading counts as "efficient" depends on the chiller. Many constant-speed chillers are most efficient at fairly high loads. Chillers with variable speed compressors can be very efficient at part load, especially when the condenser water is cool.

So the right stage-up and stage-down points come from the chiller's performance data, not from a general rule.

Try it

Loading the interactive

Low delta-T

Now, staging depends on the water's ΔT, and a problem out on the air side can throw it off. This problem is called low delta-T syndrome, and the Cooling course's lesson on low delta-T covers it in detail. Here's how it affects staging.

The office tower uses primary-secondary pumping. Each chiller has its own primary pump that pushes a fixed flow through it. Then secondary pumps with variable speed drives send water out to the building.

A short pipe called the decoupler joins the two loops, so their flows can differ. At the design ΔT of 6 °C, each 500 RT chiller needs about 70 litres per second through it. So two running chillers pass about 140 L/s.

Now suppose the AHU coils are dirty, or some control valves are stuck open. The water comes back at 10 °C instead of 12 °C. The ΔT is now 4 °C, with the same 900 RT load:

Design ΔT (6 °C)

Low ΔT (4 °C)

Flow the building needs at 900 RT

about 126 L/s

about 189 L/s

Flow through two running chillers

about 140 L/s

about 140 L/s

What happens

The chillers pass more than the building needs, and the extra returns through the decoupler

The building needs about 49 L/s more than the chillers pass. Warm return water flows back through the decoupler and mixes into the supply

Two panels comparing primary-secondary flow with two chillers passing about 140 L/s: at the design delta-T the building needs about 126 L/s and spare cold water returns through the decoupler while at a low delta-T the building needs about 189 L/s and about 49 L/s of 10 degrees C return water flows back through the decoupler into the supply

With a low delta-T, the building needs more water than the running chillers pass, so warm return water mixes into the supply through the decoupler.

So in the low ΔT case, the water going to the building is warmer than 6 °C. Some of it hasn't been through a chiller at all. The AHUs open their valves further to cover the shortfall, which draws even more flow.

The BMS sees rising supply temperature or high flow and starts the standby chiller. That's despite two chillers having 1,000 RT of capacity for a 900 RT load. The third chiller, its pumps and its tower fans all add energy, and the root cause is out on the air side.

So the lessons for the BMS are practical. Trend the chilled water ΔT, alarm when it stays low, and learn why before accepting that the plant "needs" another chiller.

Worth knowing: in Part 2 we saw how even a drifted return water sensor distorts the calculated ΔT.

Chilled water reset

You might expect a chiller plant to spend most of its time working hard. In practice it rarely does. Plants are sized for the hottest hour of the year, with full sun and a full building, and that hour is rare.

A typical building spends most of its operating hours around 50% to 75% load, and very little time at full load.

The industry's standard chiller rating reflects this. AHRI (the Air-Conditioning, Heating, and Refrigeration Institute, a US standards body) publishes a part-load rating. It combines a chiller's efficiency at 100%, 75%, 50% and 25% load into one figure.

Full load gets only about 1% of the weight, and most of it sits on the 50% to 75% band. That's a standard weighting for comparing chillers on paper, not a record of how many hours your building spends at each load.

The Cooling course's lesson on chiller part-load efficiency explains it.

So part-load efficiency decides most of the plant's energy use, and part-load efficiency depends heavily on control. That's where the two resets come in.

To see why they work, we need one more idea. A chiller's compressor has to lift heat from the cold chilled water up to the warmer condenser water.

We call the temperature gap between the two the lift. The bigger the lift, the harder the compressor works and the more power it draws.

Chilled water reset shrinks the lift from the cold side. Instead of holding 6 °C all day, the BMS raises the chilled water setpoint when the building's cooling demand is light.

On a mild or half-empty afternoon, the AHUs don't need the coldest possible water. So the BMS lets the setpoint rise by a degree or two, and the compressors draw less power. When demand rises again, the reset brings the setpoint back down.

So how does the BMS decide how far to reset? It watches the AHUs, and a common method looks at their chilled water valve positions.

If even the busiest AHU's valve is only partly open, there's spare capacity, and the setpoint rises a little. If any valve is nearly fully open, that AHU is struggling, so the setpoint comes back down.

That's the feedback idea from Part 5 again, applied to the whole plant instead of one valve. The new setpoint goes to the chillers through the writable point we saw in Part 10's mapping table.

Two limits keep the reset safe in a Malaysian building:

  • Humidity. The chilled water coil also takes moisture out of the air. Warmer chilled water removes less of it, so indoor humidity can rise. The reset needs an upper limit, and it should back off if space humidity climbs, where the AHUs measure it.
  • Pumping energy. Warmer water carries less cooling per litre, so the AHU valves open further and the secondary pumps move more water. Part of the chiller saving goes on pump energy, so tune the reset by watching total plant kW, not chiller kW alone.

The Cooling course covers humidity. And what if the BMS loses the AHU valve signals, for example during a network fault (Part 11)? A well-written sequence goes back to the design setpoint of 6 °C instead of guessing.

Condenser water reset

The other side of the lift is the condenser water coming back from the cooling towers. The colder that water is, the smaller the lift and the less power the compressor draws.

Condenser water reset runs the tower fans harder to bring the condenser water temperature down. That spends extra fan energy to save compressor energy, and it's usually a good trade, because the compressor is by far the larger motor.

There's a rule of thumb you'll often hear. Every 1 °F (about 0.6 °C) of warmer condenser water raises chiller power by about 1.0 to 1.5%.

But there's a limit. Beyond some point, the extra fan power costs more than the compressor saves. So a good sequence looks for the lowest total of chiller and tower fan power. It also respects the chiller manufacturer's minimum condenser water temperature.

There's a physical floor too, and in Malaysia it matters a lot. A cooling tower cools water by evaporation, and evaporation is limited by the wet-bulb temperature.

That's the temperature a wet surface reaches when air blows over it, and it depends on how humid the air is. No amount of fan power can cool the condenser water below the wet-bulb temperature, and in practice the water leaves a few degrees above it.

So a cooling tower in a dry climate can make much colder water than an identical tower here. Malaysia's humid air keeps the wet-bulb high all year.

In the tropics, condenser water reset is about capturing every degree the humid air allows. And that's a narrower range than textbooks written for temperate climates assume.

Keeping it switched on

So put the three decisions together, and the point is clear. The same plant can be efficient or wasteful with no change to its equipment. It depends on whether staging and the two resets are switched on and tuned.

Many plants have these sequences in the BMS but not running. Years ago, during a commissioning problem, someone put the plant into a fixed manual mode, with all chillers on and setpoints at their coldest. Then nobody switched the automation back on.

Part 8 showed how overrides like this hide in a BMS. The hardware can do the job, but the control isn't doing it. That plant can run past 1.0 kW/RT for years while an identical plant nearby holds 0.6.

So how much is at stake? Studies report meaningful plant-wide savings from optimised sequencing and reset. But the headline figures, often anywhere from 10% to 40%, depend heavily on how poor the starting point was.

A plant that's already reasonably well run has less to gain, and a plant stuck in manual mode has a lot. For plants that are already decent and add continuous monitoring and optimisation, a more modest 5% to 10% is typical.

For a sense of scale in the office tower, take the 900 RT peak. At the measured 0.95 kW/RT, that's about 855 kW of plant power. At the design 0.85 kW/RT, it would be about 765 kW, which is a difference of about 90 kW at that moment.

Closing that gap is mostly a matter of control. That means:

  • confirming the sequences are running
  • fixing a low ΔT
  • trending kW/RT so any drift shows up

The air side

So the plant now makes the right amount of cold water, at the right temperature, with the fewest machines. But the chilled water is only halfway to the people. The AHUs and fan coil units still have to use it to cool and dry the air on each floor.

So once the chilled water reaches AHU-12A, how does the BMS control the airflow, the air temperature and the fresh air on level 12? That's Part 13: How a BMS Runs the Air Side.

Check your understanding

1. On a morning when the office tower's load is 350 RT, why should the BMS run one chiller instead of both duty chillers?

Show the answer

One 500 RT chiller can carry 350 RT at about 70% of its capacity. Running two would leave each at about 35%.

It would add a second condenser water pump, more tower fans and more running losses, for no extra cooling. The best loading for a particular chiller comes from its performance data.

2. Why can't condenser water reset bring the tower water down to, say, 20 °C in Kuala Lumpur?

Show the answer

A cooling tower cools water by evaporation, which can't cool it below the outdoor wet-bulb temperature. In practice the water leaves a few degrees above that.

Malaysia's humid air keeps the wet-bulb temperature high, so the reset can only capture the degrees the weather allows.

Recap

  • The chiller plant is the office tower's largest electricity user, and its efficiency is measured in kW/RT.
  • The BMS measures the cooling load from chilled water flow and ΔT.
  • Staging runs the fewest chillers that meet the load, with deadbands and delays to stop short cycling.
  • A low ΔT can make the plant start chillers it doesn't need, so trend ΔT and alarm on it.
  • Most operating hours are at part load, where control matters most.
  • Chilled water reset raises the setpoint when demand is light, within humidity and pumping limits.
  • Condenser water reset lowers the tower water temperature as far as the wet-bulb temperature and total fan power allow.
  • None of it saves anything unless the sequences stay switched on.

Go deeper on video (optional)

This video walks through the main ways a chiller plant is made more efficient, including the staging and reset strategies above. It's optional.

This is Part 12 of 16 in Cobler's Building Automation and BMS Fundamentals course. Previous: Who Owns the BMS Network? Access, Backups and Recovery. Next: How a BMS Runs the Air Side: VAV, Static Pressure Reset and Fresh Air.

Cobler builds CobiNeural, a platform that shows a facility team its building's energy, water and indoor air data as live numbers across the whole site. To see how your building performs, talk to us.

FAQ

Frequently asked questions

Ask us about this topic

Something in this article you want to dig into — or a situation in your own building it doesn't quite cover? Send us your question. We don't run public comments; the team replies to you directly by email.

0/500

Keep reading